Status
Under construction
Length
11 km
Voltage
110 kV
Capacity
50 MVA
COD
2030
The project involves the construction of the new 110/12 kV Margarita substation and the new power line that will connect the Margarita substation with the Agua Santa substation.
This new infrastructure will strengthen the Valparaíso electricity grid and improve the quality and reliability of the power supply in the municipality of Quilpué.